Cathedral Village
Details
Client: Cathedral Village
Delivery System(s): CM at Risk
SF: 200,000-sf addition & 16,000-sf of renovations
Cost: $77.5 million
Phase II – $60 million
Phase III – $10.2 million
Phase IV – $7.3 million
Completion Date: Expected 2026
Phase II – October 2020
Phase III – May 2023
Phase IV – 2026
Architect: Spiezle Architectural Group
Overview
Phase II included exterior enhancements, new lighting, and a 200,000-square-foot, two-story building addition. Phase III featured a new bus drop-off, entry and façade renovations, corridor upgrades, and selective demolition. Phase IV, currently underway, includes corridor renovations in Buildings G and H, along with a new domestic water service across the campus. Through careful scheduling and collaboration, PJ Dick successfully delivered each phase on time and within budget while preserving resident comfort and safety.